Faribault County Public Works Director Tells Commissioners Most Highway Projects for 2022 are Complete

The Faribault County Board of Commissioners learned Tuesday that most of the highway projects scheduled for this year are either complete or nearing completion.

Public works director Mark Daly says all of the work is done on County Roads 28 and 30 and the north part of County 31 is complete except for getting fog lines painted.  Also County Road 21 is complete, with the exception of shouldering work.

Daly said bridge work has been delayed this summer due to supply issues and work on those will not begin until late July or August.

In other business, the Commissioners made a motion to approve payment number two for the courthouse heating, ventilation and air conditioning project in the amount of $27,759.